Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Construction Design Ltd
14 Tynwald Street
Douglas
IM1 1BG
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Ann Clayton Proposal: Construction of a garage with living accommodation over to replace existing flat roofed garage at: 114 Summerhill Road
Onchan
Isle Of Man
IM3 1NJ
which was considered on 20th June 2008, subject to compliance with the conditions specified below.
Date of Issue: 23rd June 2008
Murray House
Mount Havelock
Douglas
Secretary to the Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to drawing no.s 580/001, 580/003 and 580/004 date stamped the 1st February 2008.
- The accommodation created by this approval must only be used as accommodation ancillary to that of the existing dwelling. For the avoidance of doubt, no approval should hereby be conferred by this approval for the use of the new accommodation as a separate dwelling.
- The glass in rooflight serving the shower room must be glazed and maintained thereafter using frosted glass. The level of obscuration used must be no less than level 5 as detailed on the Pilkington's textured glass range or equivalent.
08/00195/A
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/ dlge/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.