Mr Hugh Logan Bridge Court 10 Bridge Street Castletown
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Hartford Homes Ltd Proposal: Registered Building consent for renovations and erection of extensions (In association with 07/02384/GB) Registered Building Nos. 98. at: Conister House 16 - 18 Finch Road Douglas Isle Of Man IM1 2PT
which was considered on 11th April 2008, subject to compliance with the conditions specified below.
Date of Issue: 16th April 2008
Murray House Mount Havelock Douglas
Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This consent relates to the renovation, erection of extensions and construction of a new car park as shown in drawing numbers 1112-00, 1112-01, 1112-02, 1112/03/A, 1112/04/A, 1112/05/A, 1112/06/A, schedule of works and design statement date stamped 20th December 2007.
- Prior to the commencement of any building works, a photographic survey must be undertaken to record all existing internal and external features of interest and provided for
approval by the Planning Authority. Such a record to be prepared in consultation with the Conservation Officer of the Department.
- Prior to the commencement of any building works, large scale (1:20 / 1:10) detail drawings of the railings and associated gates on the Finch Road elevation shall be submitted to and approved in writing by the Planning Authority and thereafter the works shall be carried out in accordance with the approved details.
- PRIOR to the commencement of any building works, further large scale (1:20 / 1:10) detail drawings are to be produced of the new internal doors to indicate the framing detail, architrave and materials are submitted to and approved in writing by the Planning Authority and thereafter the works shall be carried out in accordance with the approved details.
- Prior to the commencement of any building works, a schedule of replacement windows is to be drawn up. The schedule is also to include, large scale (1:20 / 1:10) detail drawings of the windows to be replaced to indicate the framing detail, material and glazing bar profiles. This is to be submitted to and approved in writing by the Planning Authority and thereafter the works shall be carried out in accordance with the approved details.
- Prior to the commencement of works, a sample of the roofing slate must be submitted to and approved in writing by the Planning Authority and thereafter the works shall be carried out in accordance with the approved details. The slate is to match the existing in respect of material, colour, texture and size.
- Prior to the commencement of works, details of the disabled access platform to be installed shall have been submitted to and approved in writing by the Planning Authority and thereafter the installation of the platform shall be carried out in accordance with the approved details.
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This decision notice is issued in accordance with Regulation 9(1) of the Registered Building Regulations 2005.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.