Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
BRW Architectural Thie Gennal Crossag Road Ballasalla IM9 3DX
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: Mr & Mrs Morris Proposal: Elevational amendments to approved conversion of outbuildings to living accommodation (99/01022B) at: The Barn Ballig Farm West Baldwin Isle Of Man IM4 5EU
which was considered on 21 June 2006, subject to compliance with the conditions specified below.
Date of Issue: 3 July, 2006 Murray House Mount Havelock Douglas Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to Drg. No’s 06/11/01 and 02, submitted as part of this application and date stamped 7th April 2006.
NOTE There are Underground Cables/Overhead Lines present in the area indicated in your Planning Application. Please contact Anthony Kinrade or Ian Horsey, Operations and Maintenance Department, Network Services, Manx Electricity Authority, (Tel: 687705) to discuss working practices around Cables and
Overhead Lines which may be required to be diverted before any work can be carried out on site.
Contact the MEA for Electrical Site Safety 5 documents, (Tel: 687766), before any work is carried out on site. All work to be carried out with reference to Health and Safety Executive Guidance Notes HS(G)47 & GS6.
NOTE For water connections that comprise more than a single connection to a water main or service, or where new water mains and hydrants will be required, the applicant should contact the Isle of Man Water Authority Planning and Projects Section, telephone 695958.
This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to down load from the Department’s website www.gov.im/dlge/planning/plan
You should note that a copy of the Officer’s report which led to the decision being made, along with any correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.