Planning Approval Decision Notice
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
Mr Hugh Logan Bridge Court 10 Bridge Street Castletown
In pursuance of powers granted under the above Act and Order the Department of Local Government and the Environment does hereby APPROVE the following application made on behalf of:
Name: IM9 Ltd Proposal: Addition of a dormer on approved residential development (05/92112B) at: Former Methodist Church Hall Gellings Avenue Port St. Mary Isle Of Man
which was considered on 1 June 2006, subject to compliance with the conditions specified below.
Date of Issue: 8th June, 2006 Murray House Mount Havelock Douglas
Secretary Planning Committee
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This permission relates to the addition of lift accommodation as shown in drawings reference 1029-02, -04C and -05C all received on 13th April, 2006. The development must be otherwise carried out in accordance with the terms and conditions of PA 05/92112.
NOTE There are underground cables/overhead lines present in the area of the application. As such the applicant/developer is advised to consult the MEA (tel: 687766) before any work is carried out.
This decision was made by the Director of Planning and Building control in accordance with the authority delegated to him under Article 3(13) of the Town and Country (Development Procedure) Order 2005.
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to down load from the Department’s website www.gov.im/dlge/planning/plan
You should note that a copy of the Officer’s report which led to the decision being made, along with any correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.