Loading document...
Gordon Clarke The Design Studio, Carmodil Beg Glen Road Ballaugh, Isle of Man IM7 5JD
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Dalmatian Limited, Ref 25/90378/B, for the Extension to existing shed for hay production/storage at Blue Point Yard Ballawhane Farm Leodest Road Andreas IM7 3EG .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: The countryside is protected from development and an exception is being made on the basis of agricultural need. As such the building must be used for the purposes for which it is approved and removed if no longer needed.
Reason: to align with the details submitted and towards creating cohesion across the buildings external appearance.
This approval relates to the following:
This decision has been made for the following reasons(s) It is accepted that there is a recognised agricultural justification to meet with General Policy 3, and the proposed building by reason of its siting, size, scale and design is considered to have an acceptable impact on the character and appearance of the countryside in line with Environment Policies 1, 2 and 15 of the Isle of Man Strategic Plan 2016 and not to undermine Landscape Character Appraisal area F2. It is also considered that the proposal has an acceptable amenity impact on the neighbours in line with General Policy 2 (g) and Environment Policy 22.
Date of Issue: 22nd July 2025
J CHANCE Director of Planning and Building Control
Guidance Note This decision was made by a Principal Planner in accordance with the authority delegated to them. This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation. A copy of the Officer’s report and any correspondence which informed the assessment and decision is available to view on the Government’s website (via https://pbc.gov.im/online-applications/)
Implementation The decision does not become final until either
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain:
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated. An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application (should one have been received) may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.
Copyright in submitted documents remains with their authors. Request removal
View as Markdown