Loading document...
Manx Telecom Douglas Central Telephone Exchange Dalton Street Douglas IM1 3PQ
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Manx Telecom, Ref 25/90113/B, for the Installation of a telecommunications base station at Kings Court Ramsey Isle Of Man IM8 1LW .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: To ensure that any redundant infrastructure is removed and to comply with Strategic Plan Infrastructure Policy 3.
Reason: To ensure the mobile antenna equipment is adequately secured to the building against wind loading to prevent any deviation of the equipment leading to potential hazards.
This decision relates to drawings and supporting information submitted on 5th February 2025, referenced; 100, 101, 102, 103, 104, 105, 106, 107, 108, 109
ICNIRP Compliance Report dated 28/03/25. This decision has been made for the following reasons(s) The proposed application is not considered to harm the use and enjoyment of neighbouring properties nor would it result in any adverse impact upon the streetscene or this part of the roof top and would comply with Spatial Policy 5, General Policy 2 (b,c,g,m) Environmental Policy, 22, and Infrastructure Policy 3 of the IoM Strategic Plan.
Date of Issue: 1st May 2025
J CHANCE Director of Planning and Building Control
Guidance Note
This decision was made by the Planning Committee in accordance with the authority delegated to it.
This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which informed the assessment and decision is available to view on the Government’s website (via https://pbc.gov.im/online-applications/)
Implementation A determination to grant planning approval does not have effect —
Development must be carried out in accordance with the approved plans and any attached conditions (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal can only be made by a person who has been accorded rights to do so, must be in writing, include the appropriate fee and be submitted to the Department within 21 days of the date of this Notice.
Guidance on how to appeal is available at gov.im/howtoappeal
Copyright in submitted documents remains with their authors. Request removal
View as Markdown