28 February 2025 · Head of Development Management (Stephen Butler)
Field 311835, Glenfaba Road, Peel, Isle Of Man, IM5 1dx
This application sought to satisfy condition 10 of the previously approved planning permission PA 23/01407/B, which required a report of an Autumn 2024 fungi survey for field 311836, including a grassland fungi management regime, to be approved before development commencement.
Click a button above to find applications similar to this one.
See how this application compares to similar ones — policies, conditions, and outcomes side by side.
The submitted Fungi Report was deemed sufficient to satisfy condition 10 of PA 23/01407/B after consultation with the Ecosystems Policy Team, who confirmed on 17.02.2025 that the information meets the…
Pleased to confirm that the information satisfies the relevant clauses of condition 10; content with the management regime specified in Section 4.6 of EPR's Fungi Survey Technical Note for a minimum of 5 years post construction.
Manx Utilities submitted a Landscape and Ecological Mitigation and Management Plan (LEMMP) in response to condition 10 of PA 23/01407/B, detailing fungi survey results and comprehensive mitigation measures for biodiversity at the Peel Wastewater Treatment Works site.
Key concern: potential pollution impacts to West Coast Marine Nature Reserve
Manx Utilities
Support"No development shall take place... until a scheme... for the enhancement of biodiversity on the site... has been submitted to and approved" (Planning Condition 4); Wherever reasonably practicable, measures will be implemented to protect fungi; Reinstatement and creation of new hedgebanks will in time create a net increase in nesting habitat; This LEMMP sets out details of the delivery of biodiversity enhancements and mitigation measures
Conditions requested: C3 Biodiversity Mitigation Plan: scheme detailing measures for protection of trees, sod banks, and Field 311836 during construction; C6 Construction Waste Management Plan to minimise waste and maximise re-use/recycling; C7 Scheme for mitigation of dust nuisance during construction; C8 Silt Management Plan, surface water runoff scheme including silt control, polluting material handling, SuDS/filtering, and erosion prevention; C9 Surface water drainage works details including design storm, pollution prevention, timetable, and lifetime maintenance plan