Planning Approval Notice 12/00816/B
Isle of Man Town and Country Planning Act 1999
The Town and Country Planning (Development Procedure) Order 2005
McGarrigle Architects Ltd 19 Mount Havelock Douglas Isle Of Man IM1 2QG
In pursuance of powers granted under the above Act and Order the PLANNING COMMITTEE of the Department of Infrastructure does hereby APPROVE the following application made on behalf of:
Name: Mannin Investments Ltd Proposal: Demolition of existing hotels and the erection of a new hotel, including integral parking and ancillary facilities (In association with 12/00817/CON) at: Former Mannin And Broadway Hotels Broadway Douglas Isle Of Man IM2 4EL
which was considered on 6th August 2012, subject to compliance with the conditions specified below.
Date of Issue: 7th August 2012
Murray House Mount Havelock Douglas
Schedule Of Conditions:
- The development hereby permitted shall commence before the expiration of four years from the date of this notice.
- This approval relates to the demolition of existing hotels and the erection of a new hotel, including integral parking and ancillary facilities (In association with 12/00817/CON) Former Mannin and Broadway Hotels, Broadway, Douglas as shown by 1431 12 P 101, 1431 12 P 102, 1431 12 P 103, 1431 12 P 104, 1431 12 P 105, 1431 12 P 106, 1431 12 P 107, 08, 1431 12 P 109, 1431 12 P 110, 1431 12 P 111 and 1431 12 P 112 all received 1st July 2012.
- The roof(s) must be finished in dark natural slate.
- The building may be used only as tourist accommodation in accordance with the definition of tourism contained within the Isle of Man Strategic Plan 2007 and for clarification may not be occupied as a person's main place of residence. At any one time a maximum of 24 rooms may be occupied for a continuous period of up to 6 months. The remaining rooms must not be used for continuous stays exceeding 4 weeks in duration and there shall be no return within 2 months unless otherwise agreed in writing with the Planning Authority.
- The car park must not be used until a traffic light system is installed and in operation at the top and bottom of the ramp to the basement to control vehicles movements.
- If within 6 months of the demolition of the existing buildings, works have not commenced on the approved development, a scheme for the restoration and landscaping of the land must be submitted to and approved in writing by the Planning Authority. The site must be developed in accordance with the approved scheme of restoration and landscaping within 3 months of written approval unless otherwise agreed in writing with the Planning Authority. The site must remain in its restored state until works commence on the approved development.
This decision was made by the Planning Committee constituted in accordance with Article 3(1) of the Town and Country Planning (Development Procedure) Order 2005.
Guidance Note
This permission refers only to that required under the Town and Country Planning (Development Procedure) Order 2005.
Any appeal against this decision must be in writing and must be received by this Department within 21 days of the date of this notice.
A form and guidance notes are available from either the Planning Office, Tel 685950, or to download from the Department's website www.gov.im/transport/planning/plan/applications/decision.xml
Please note that a copy of the Officer's report which led to the decision, together with correspondence relative to the application, is available for inspection at the Department.
The proposed development must not be commenced until either;
- The time for requesting an appeal has expired; or
- Any appeal has been determined;
Whichever is the later.