Application No.: 22/10001/AIR Applicant: Delgatie Limited Proposal: Planning application 20/01467/B - Application seeking to discharge conditions 10, 40, 42 and 43 Site Address: Marine Biological Station Breakwater Road Port Erin Isle Of Man IM9 6JA Planning Officer: Mr Paul Visigah Recommended Decision: Permitted Date of Recommendation: 30.01.2023
C : Conditions for approval N : Notes attached to conditions
It is considered that the documents, letters and emails received 14 October 2022, 16 November 2022, 25 November 2022, 13 December 2022 satisfies conditions 10, 40, 42 and 43 of the approval although these conditions will not be fully satisfied until such times as the works indicated on the documents and plans have been carried out in full and retained as such. __________________________________________________________________________
Officer’s Report SATISFACTION OF CONDITION 10, 40, 42 and 43 DESCRIPTION
1.1 This approval was granted on the condition, inter alia, that: C10. Demolition (inc protection of rock face)
No development shall take place, including any works of demolition, until a dust, noise vibration management plan and any potential run off has first been submitted to the Department in writing to be agreed.
The plan shall detail timing of said works, measures for the control and reduction of dust and noise emissions associated with demolition, earthworks, construction and track out, and arrangements for protection and monitoring of the rock face and any run off into the Marine Nature Reserve. The development shall be carried out in accordance with the plan so agreed. Any rock face protection shall not include netting.
Reason: To ensure that measures are put in place to manage and reduce dust emissions during demolition and construction to safeguard local amenity and to ensure rock face and
bird habitat and the Marine Nature Reserve is not affected by the demolition or construction.
C40. Birds/Biodiversity - demolition and construction
No works in connection with the development hereby approved (including demolition, ground works and vegetation clearance) shall commence unless a construction environmental management plan (CEMP) has been submitted to and approved in writing by the Department. The CEMP shall include, but not necessarily be limited to, the following;
No works in connection with the development hereby approved (including demolition, ground works and vegetation clearance) shall commence until a biodiversity monitoring and mitigation strategy for Fulmars, Herring Gulls has been submitted to, and approved in writing by, the Department.
The purpose of the strategy shall be to monitor the effects of development and subsequent
A report describing the results of monitoring shall be submitted to the Department at intervals identified in the strategy. The report shall also set out how contingencies and remedial action will be identified, agreed with the Department and then implemented. The
development shall be carried out in strict accordance with the approved biodiversity monitoring and mitigation strategy.
Reason: In order to protect and enhance biodiversity in the environment.
No works in connection with the development hereby approved (including demolition, ground works and vegetation clearance) shall commence unless an ecological design strategy (EDS) addressing mitigation, compensation, enhancement and restoration has been submitted to and approved in writing by the Department. The EDS shall include, but not necessarily be limited to, the following:
PROPOSAL
2.1 The applicant has provided information to satisfy these conditions: notably, Agent statement on demolition (dated 25 November 2022), an email form Agent (dated 25 November 2022), Risk Assessment on Demolition (dated 14 October 22), Agent's Statement for Construction Environmental Management Plan (dated 13 December 2022), Construction Environmental Management Plan prepared by Manx Wildlife Trust Consultancy (dated December 2022), Correspondence between the applicants and DEFA Building Control regarding Risk Assessment on Demolition, Agent's Statement for Biodiversity monitoring and mitigation strategy, Biodiversity monitoring and mitigation strategy prepared by Manx Wildlife Trust Consultancy (dated December 2022), Agents Statement for Ecological Design Strategy and Ecological Design Strategy prepared by Manx Wildlife Trust Consultancy (dated November 2022), which shows details of:
2.2 Following request for additional and revised information by the Ecosystem Policy Team, the applicant has provided amended documents accompanied by an email (dated 16 January 2023) which details the revised documents that has been provided and the conditions the revised documents refer to. The additional documents are:
2.3 The Ecosystem Policy Officer has provided a written statement via an email dated 27 January 2023 which confirms that they are content with the details provided in amended documents.
RECOMMENDATION
3.1 The documents, letters and emails received 14 October 2022, 16 November 2022, 25 November 2022, 13 December 2022 satisfies conditions 10, 40, 42 and 43 of the approval although these conditions will not be fully satisfied until such times as the works indicated on the documents and plans have been carried out in full and retained as such.
I can confirm that this decision has been made by a Principal Planner in accordance with the authority afforded to that Officer by the appropriate DEFA Delegation and that in making this decision the Officer has agreed the recommendation in relation to who should be afforded Interested Person Status.
Decision Made : Permitted Date: 21.02.2023 Determining officer
Signed : A MORGAN Abigail Morgan Principal Planner