Loading document...
Sarah Corlett Town Planning Consultancy Ltd Miss Sarah Corlett Ballachrink Croft Ballacorey Road Bride IM7 4AW
TOWN AND COUNTRY PLANNING ACT 1999 The Town and Country Planning (Development Procedure) Order 2019
In pursuance of powers granted under the above Act and Order the Department of Environment, Food and Agriculture determined to APPROVE an application by Mr Julian Wood, Ref 23/00739/B, for the Erection of dwelling to replace former dwelling "Ballatiki" at Land Of Former Ballatiki Shore Road Ballaugh Isle Of Man IM7 5AZ .
Any conditions or notes which apply to the approval are set out below. This approval is subject to compliance with any conditions listed and may not be implemented until it becomes final (see guidance notes).
Reason: To comply with Article 26 of the Town and Country Planning (Development Procedure) Order 2019 and to avoid the accumulation of unimplemented planning approvals.
Reason: To control development in the interests of the amenities of the surrounding area. This approval relates to the following drawings and documents referenced; 01, 02, 03 RevA, 04 RevA, 05 and Planning Statement, all received 22.06.23. NOTE FOR YOUR INFORMATION Please be aware that a ban on the installation of fossil fuel heating systems in any new building(s) and or extension(s), will come into force on 1st January 2025.
You therefore are encouraged to ensure that your proposed development includes alternatives to fossil fuel heating systems if you believe that such works will not be completed by that date.
To this end, if you propose an alternative, such as air source or ground source heat pump(s), or any other heating system that would require planning approval, the details of this should be addressed now. This may require you to resubmit your planning application to accommodate the alternative permitted heating system proposed.
This decision has been made for the following reasons(s) The proposed development is considered to be acceptable by providing a modern dwelling of a high standard of design, which would successfully assimilate into the wider streetscene without detriment to the character of the wider streetscene or landscape setting. The proposals comprise a more efficient use of the site than the previous dwelling in situ, whilst amounting to an environmental improvement through the use of modern buildings techniques, solar panels and an air source heat pump.
The development is considered to be provide suitable accommodation for future occupants, without detriment to the amenities of surrounding properties or giving rise to an adverse impact upon highway safety. The proposals are therefore deemed compliant with General Policies 2 and 3, Environment Policies 1 and 2, and Housing Policy 14 of the Strategic Plan.
Date of Issue: 23rd August 2023
J CHANCE Director of Planning and Building Control
Guidance Note
This decision was made by the Planning Committee in accordance with the authority delegated to it.
This decision refers only to that applied for under the Town and Country Planning Act 1999 and its subordinate legislation.
A copy of the Officer’s report and any correspondence which led to the assessment and decision is available to view on the Government’s website (via Online Services www.gov.im/Viewapplications) or at the Department’s offices Murray House, Mount Havelock, Douglas.
Implementation The decision does not become final until either
Development must progress in accordance with the plans approved under, and any conditions attached to this approval (irrespective of any changes that may separately be requested at the Building Control stage or by any other Statutory Authority). This approval does not remove the need to also comply with any other relevant legislation.
Any conditions requiring certain works, submissions etc. prior to commencement of development must be fulfilled prior to work starting on site. Failure to adhere to this approval and meet the requirements of all conditions may invalidate this approval or result in formal enforcement action.
Appeal Any appeal must be in writing and submitted to the Department within 21 days of the date of this Notice. The appeal must contain:
Failure to meet all of the relevant above requirements will mean that the appeal cannot be validated.
An appeal form and more detailed guidance are available either from Planning & Building Control, Tel 685950, or from the Department’s website www.gov.im/planningappeal
If this decision becomes final because there is no appeal, the Department’s public reference copy (counter copy) of the planning application (should one have been received) may be collected by the applicant or their agent from Murray House. Please note that if the counter copy of the application is not collected within thirty days following the last date on which a planning appeal can be made it will be destroyed without further notice.
Copyright in submitted documents remains with their authors. Request removal
View as Markdown